Saltonstall Park Project
Project Overview | |
Project Status | Construction Starting October 2024 |
Project Features | plaza, lawn, grove of trees, benches farmers market, a pavilion for concerts |
Funding Source | Community Preservation Act Fund |
City Departments & Committees | Department of Public Works (DPW) Recreation Department of Community Development and Planning (DCDP) Live Well Watertown Community Preservation Committee |
Design Team | MDLA Segar Architects, Inc AVID ACENTECH H+O Structural Engineering |
Construction Contractor | UEL |
Timeline
Design & Community Input | |
Construction Drawings | |
Construction | Fall 2024 - Spring 2024 |
Saltonstall Park Project Overview
Saltonstall Park is an open space park adjacent to City Hall, and a gathering location for various City events such as Faire on the Square, The Summer Concert Series, and the Farmers Market. The goals of the Saltonstall Park Project include enhancing the upper area of Saltonstall and beautifying the park while also improving safety and accessibility.
This will be accomplished through landscaping upgrades, improving pedestrian accessible walkways, and enhancing the streetscape with benches and dark sky compliant lighting as well as installing a permanent covered performing space.
The DPW recently worked with the Veteran's Office to renovate the plaza around the flag poles to add the flag for the new 6th service branch of the armed forces. They have also been in continuous discussions with the Planning Department to ensure that these renovations will allow the park to be further utilized by the Watertown community not only by enhancing the current events that take place in the park, but by enabling additional events to be scheduled in the future.
Community Feedback
Over 800 residents participated in helping to select a structure to be installed at Saltonstall Park as part of the park’s redesign project! Across social media, FlashVote, Email & In Person Voting at the Library there was a clear Favorite!
Concept E took home 40% of the overall vote followed by Concept A with 23%, Concept B with 17%, Concept D with 11% and finally Concept C with 9%.
Thank you for you help! Please visit the page with the answers to common questions about the project
Community Meeting Recordings
Please find links to below to watch Community Meetings that have been held thus far via ZOOM:
- Community Meeting #2 Recording – February 7, 2023
- Community Meeting #3 Recording – February 23, 2023
- Community Meeting #4 Recording – March 2, 2023
Meeting Presentation & Final Designs PDFs
- Onsite Meeting #1 – Saltonstall Park Site Improvements (PDF) – November 1, 2022
- Community Meeting #2 – Site Design Recap & Shade Structure (PDF) – February 7, 2023
- Community Meeting #3 & #4 Site Design Recap and Shade Structure (PDF) – February 23, 2023 & March 2, 2023
- Saltonstall Park Improvements-L100_Construction Drawing (PDF) - June 30, 2023
Construction Updates
The Saltonstall Park Improvements Project will begin in the second week of October, 2024. Construction will continue from Fall 2024 to Spring 2025 and the upper Saltonstall Park work area will be closed to the public during this time. The project includes upgrades to the walkways, stairs, and the installation of a new permanent stage.
If you have any questions or concerns regarding this project, contact the Watertown Department of Public Works at 617-972-6420.